Mulberry Child Care Center 2

Project Description

The center will be located near the southeast corner of Serra Street, adjacent to the recently completed Child Care Center, and will back up to El Camino Real, across from the family neighborhood of Escondido Village. The new child care facility will front Olmsted Road with a covered main entry. A fence will enclose the center’s play yard that lies west of the building. The center will encompass 9,411 gsf in a residential-type, two-story building. It will include amenities similar to those at the other existing centers on campus, such as tree-shaded outdoor play areas.

 Project Data

Department/School President/Provost (PRES/PROV)
Architect Hoover Architects
Contractor Building & Beyond, Inc.
Gross Square Feet 9,411
Construction Schedule Jan 2011-Oct 2011
Project Manager

Mark Bonino

Project Website N/A

 


Current Activity

Current Work
  • High volt in place
  • Exterior is getting painted
  • Waiting for alarm permit
  • Gas approval expected this week and underground will commence next week
  • Interior doors ordered
  • Exterior concrete will start in two weeks
Safety Reminders
  • General Construction Hours: Monday through Friday 8:00am-5:00pm
  • Expect construction vehicles, heavy machinery, loud noise, and dust around the job site
  • For your safety and the safety of the workers, please abstain from entering the job site.
Notes
  • For additional information on this project contact the project manager, Mark Bonino (650) 723-0022.